Data centre planning applications subject to lengthy delays, report finds

By
BE News Team

Share this:

Data centre planning applications are being delayed by 490 days on average, driven largely by objections related to inadequate community engagement, unclear community benefits, design, infrastructure constraints, and energy use, according to a new report published by Hoare Lea.

The company’s societal insights team analysed 33 disputed applications to understand the underlying reasons for rejection and delay, with rejections frequently citing policy non-compliance, unsuitable locations and insufficient energy strategies.

Concerns also exist around environmental impacts, greenbelt land, and controversial government interventions overriding local planning decisions.

Carl Walker, head of societal insights at Hoare Lea, said: “Success will be judged not only by new infrastructure, but also by the skills, growth and opportunities delivered to local communities, who’s needed must be recognised in the planning process.”

Get the latest news!

Don’t miss our top stories and need to know news every day in your inbox.